Westfield – Associated paving work across the city beginning September 11th through September 20th, between the hours of 7:00 AM and 6:00 PM, weather dependent, will be as follows:


Monday 9/11: Milling of pavement on Granville Road.


Tuesday 9/12: Milling of pavement on Granville Road and Western Avenue.


Wednesday 9/13: Milling of pavement on Westwood Road.


Thursday 9/14: Milling of pavement on Prospect Street.


Friday 9/15: Preparatory work on Old Holyoke Road.

 

Monday 9/18: Milling of pavement on Holyoke Road, Dry Bridge Road, and Sandy Hill Road.

Structure adjustments begin (in same order as streets milled).


Tuesday 9/19: Milling of pavement on Stuart Place and Stuart Circle.


Wednesday 9/20: Miscellaneous milling cleanup.