Paving: City-wide
Westfield – Associated paving work across the city beginning September 11th through September 20th, between the hours of 7:00 AM and 6:00 PM, weather dependent, will be as follows:
Monday 9/11: Milling of pavement on Granville Road.
Tuesday 9/12: Milling of pavement on Granville Road and Western Avenue.
Wednesday 9/13: Milling of pavement on Westwood Road.
Thursday 9/14: Milling of pavement on Prospect Street.
Friday 9/15: Preparatory work on Old Holyoke Road.
Monday 9/18: Milling of pavement on Holyoke Road, Dry Bridge Road, and Sandy Hill Road.
Structure adjustments begin (in same order as streets milled).
Tuesday 9/19: Milling of pavement on Stuart Place and Stuart Circle.
Wednesday 9/20: Miscellaneous milling cleanup.